At last the major demolitions are nearing completion and the majority of the building is ready for the new concrete floors to be poured on Monday, this means work can begin on re-building the walls and everyone should start to see a difference on the webcam.
This is what happens when you get a hole in your ground source heat pipes.. Sintec were back onsite this week to grout the pipes into the boreholes this involves pressure testing them first to make sure they'll work when the system is commissioned -good times. They couldn't get pressure in the last pipe which generally means theres a hole in it and they have to pull the 70m pipe out by hand and replace it -bad times
The long awaited removal of the electricity pole, sited in the middle of the Lawson Park meadow, was completed this week. With a great deal of equipment, monster trucks and men on mobile phones in attendance, the removal of the pole and undergrounding work seemed to be completed relatively smoothly, it only seemed to be the small matter of flicking the switch to turn our electricity back on that was a problem, hence the delay in posting pictures of this great (and very expensive) event.
Lecks temporary site manager oversees progress while Barry takes a well earned break.
After 6 weeks the drilling is finally complete and the rig is taken off site..phew